Refurbishment & Improvement works at Tanjung Manis Port Site

18 July 2013

Construction Project Billboard

Naim Engineeering & consultant's site offices

Works progressing against the background of congested port

On-going piling
The proposed refurbishment and improvement works of existing Tanjung Manis Port  which commenced on 13th March, 2013 for its land-based package are progressing with sand filling & piling works currently underway.The whole project, both sea and land-based are expected to be completed by 12th March, 2015.